SMRP metric 5.5.72

Contractor hours (SMRP Metric 5.5.72)

The short-form equation is (Hcon / Hm) × 100. Every symbol is defined in the variable key below.

Share of maintenance hours worked by contractors.

(Hcon / Hm) × 100

Hcon = contractor labor hours  ·  Hm = total maintenance labor hours

Ex. 1,200 contractor hours of 8,000 total maintenance hours → 15%.

Edition note. The formula on this page follows the 7th edition of SMRP Best Practices. Where we know the 6th and 7th editions differ, we say so on the relevant metric pages. If a question quotes a formula, use the formula in the question.

This page is study material for the closed-book CMRP exam. It is not official SMRP text. Learn the short-form equation and the variable key well enough to write them from memory.

Practice this metric in exam-style questions

The free diagnostic and the $99 practice-exam pack include original calculation and definition items. They are not official exam questions.

Independent exam prep · Not affiliated with SMRP