SMRP metric 2.1.1 · Revised in the 7th edition
OEE Formula for the CMRP Exam
The short-form equation is OEE = A × P × Q. Every symbol is defined in the variable key below.
Scheduled-time effectiveness. Do not mix this with OEE 1 (utilization and scheduling losses over total available time) or with TEEP.
OEE = A × P × Q
A = availability (metric 2.2) · P = ra / rbest (actual rate / best rate); if cycle times, P = tbest / tactual · Q = good units / total units. This is the OEE 2 form: while the asset is scheduled to operate. Availability is net of idle time.
Ex. A = 0.90, P = 0.95, Q = 0.98 → OEE = 0.838 (83.8%).
Edition note. Revised in the 7th edition. This is the OEE 2 form: A × P × Q on scheduled time, with availability net of idle time. When the data are cycle times, this site uses P = t_best / t_actual (Guideline 2.0, and the rule that performance cannot exceed 100%). The 2.1.1 formula box in the 7th edition prints actual ÷ best for cycle time, which inverts the ratio. If a question quotes a formula, use the formula in the question.
This page is study material for the closed-book CMRP exam. It is not official SMRP text. Learn the short-form equation and the variable key well enough to write them from memory.
Frequently asked questions
Is OEE the same as TEEP?
No. OEE is A × P × Q while the asset is scheduled to operate. TEEP multiplies the same three factors by utilization, so idle time is in the measure. Do not report a TEEP figure as OEE.
Which cycle-time formula should I use?
When the data are cycle times, this site uses P = t_best / t_actual, which matches Guideline 2.0 and the rule that performance cannot exceed 100%. The 2.1.1 formula box in the 7th edition prints actual ÷ best, which inverts the ratio. If a question quotes a formula, use the formula in the question.