SMRP metric 5.4.11 · Revised in the 7th edition

PM & PdM work orders overdue (SMRP Metric 5.4.11)

The short-form equation is Sort overdue PM/PdM WOs into age or % past-interval buckets; report the count or share in each.. Every symbol is defined in the variable key below.

A distribution of overdue PM/PdM work, not a single compliance percent.

Sort overdue PM/PdM WOs into age or % past-interval buckets; report the count or share in each.

Typical time buckets: 1–30, 31–90, and >90 days overdue; or 0–25%, 25–50%, and >50% past the planned interval.

Ex. 18 overdue PM/PdM work orders: 11 are 1–30 days overdue, 5 are 31–90, and 2 are more than 90 days overdue. Report each bucket, not a single overdue count.

Edition note. This metric is listed as revised in the 7th edition of SMRP Best Practices. The formula on this page is the 7th-edition form. The exam may still use earlier wording, so if a question quotes a formula, use the formula in the question. Unconfirmed 6th-edition equations are not shown.

This page is study material for the closed-book CMRP exam. It is not official SMRP text. Learn the short-form equation and the variable key well enough to write them from memory.