Ready backlog (SMRP Metric 5.4.9)
The short-form equation is Wr / C. Every symbol is defined in the variable key below.
Weeks of work that can start now. Parts-not-ready work stays out of this figure and off the weekly schedule.
Wr / C
Wr = ready-to-schedule hours (fully planned, parts available) · C = weekly crew capacity
Ex. 1,200 hours are fully planned with parts on hand, and weekly crew capacity is 800 hours → 1.5 weeks of ready backlog.
Edition note. The formula on this page follows the 7th edition of SMRP Best Practices. Where we know the 6th and 7th editions differ, we say so on the relevant metric pages. If a question quotes a formula, use the formula in the question.
This page is study material for the closed-book CMRP exam. It is not official SMRP text. Learn the short-form equation and the variable key well enough to write them from memory.
Practice this metric in exam-style questions
The free diagnostic and the $99 practice-exam pack include original calculation and definition items. They are not official exam questions.
Independent exam prep · Not affiliated with SMRP