Planned Work Formula (SMRP Metric 5.3.1)

The short-form equation is (Hp / Hm) × 100. Every symbol is defined in the variable key below.

Share of maintenance hours that were executed against a plan.

(Hp / Hm) × 100

Hp = planned hours executed  ·  Hm = total maintenance hours

World-class target often shown as >90% — a target, not a definition.

Edition note. This metric is listed as revised in the 7th edition of SMRP Best Practices. The formula on this page is the 7th-edition form. The exam may still use earlier wording, so if a question quotes a formula, use the formula in the question. Unconfirmed 6th-edition equations are not shown.

This page is study material for the closed-book CMRP exam. It is not official SMRP text. Learn the short-form equation and the variable key well enough to write them from memory.

Frequently asked questions

Is planned work the opposite of reactive work?

Not exactly. Planned work is hours that had a job plan, over total maintenance hours. Reactive work is break-in hours. A job can be planned and still be reactive if it broke into the schedule.