SMRP metric 5.3.2

Unplanned Work vs Reactive Work

The short-form equation is (Hup / Hm) × 100. Every symbol is defined in the variable key below.

Share of hours that never had a job plan. Not the same as reactive (break-in) work.

(Hup / Hm) × 100

Hup = unplanned hours  ·  Hm = total maintenance hours

Ex. 1,200 hours never had a job plan, of 8,000 total maintenance hours → 15%. That is not the same figure as reactive (break-in) work.

Edition note. The formula on this page follows the 7th edition of SMRP Best Practices. Where we know the 6th and 7th editions differ, we say so on the relevant metric pages. If a question quotes a formula, use the formula in the question.

This page is study material for the closed-book CMRP exam. It is not official SMRP text. Learn the short-form equation and the variable key well enough to write them from memory.

Frequently asked questions

Is unplanned work the same as reactive work?

No. Unplanned work (5.3.2) is hours that never had a job plan. Reactive work (5.4.1) is hours that broke into the schedule. Keep the two measures separate.