Actual cost to planning estimate (SMRP Metric 5.3.3)
The short-form equation is Cact / Cpl. Every symbol is defined in the variable key below.
Cost performance of planned jobs. 1.00 is on estimate; above 1.00 is over plan.
Cact / Cpl
Cact = actual cost · Cpl = planned cost
Ex. Actual cost $11,000 on a $10,000 plan → 1.10, or 10% over the estimate.
Edition note. This metric is listed as revised in the 7th edition of SMRP Best Practices. The formula on this page is the 7th-edition form. The exam may still use earlier wording, so if a question quotes a formula, use the formula in the question. Unconfirmed 6th-edition equations are not shown.
This page is study material for the closed-book CMRP exam. It is not official SMRP text. Learn the short-form equation and the variable key well enough to write them from memory.
Practice this metric in exam-style questions
The free diagnostic and the $99 practice-exam pack include original calculation and definition items. They are not official exam questions.
Independent exam prep · Not affiliated with SMRP